Finally some nice weather to help us move along with the construction along Lakeshore Drive. Here is the current schedule the contractors are working towards as long as the weather cooperates.
Concrete work – south curb in Cottage area will be complete by June 25
- north and boulevard will be completed by August 13
- curb in Centennial Park will be completed by July 4
- curb along 50A Avenue and 40 Street will be complete by July 16
- curb in Marina area will be complete by July 16
- banding and boulevard in Marina area will be complete by August 6
Electrical – street light bases and conduit complete in Cottage area by June 25
- street light bases complete in Marina area
- street light bases and conduit to be installed along 50A Ave and 40 St. by July 1
- contractor will come back in August/September to finish Commercial area and Centennial Park
Please be aware that at the intersection of 50 Street and Lakeshore drive the traffic lights are being relocated and repaired, so this intersection will be controlled by a temporary 3 way stop.
Once again Thank You for your patience through the construction and we will do our best to ensure work is completed in a timely manner.
Due to FOIP please do not leave your contact information in your posts.
If you would like to be contacted or added to our e-mail updates, please send an e-mail to dkelham@sylvanlake.ca with a request to be added to “Lakeshore Re-Development Stage 2”
Please check back regularly and the Town will do its best to keep everyone up to date.